GL-PCT A II 6.1.2 International filing date has already been accorded

If the requirements under Art. 11(1) have already been fulfilled and the international filing date has been accorded, the wrong element or part will be replaced with the correct one and the international filing date will be changed to the date on which the correct element or part was received, unless the applicant requests that the correct element or part be disregarded under Rule 20.5bis(e). The EPO as receiving Office follows the procedure outlined in AI, sections 310 and 310bis.[R. 20.5bis(c); ]

4 references found.

Click X to load a reference inside the current page, click on the title to open in a new page.

EPO PCT GL - A Formalities Examination

PCT Articles

PCT Implementing Rules